29/08/2010

Metrix Mouthpiece

Metrix mouthpiece = article fronted by Sion Barry in the Western Mail of 27 August St Athan defence college would be good for Wales – and UK taxpayers Aug 27 2010 by Sion Barry,

 Numbers of Trainees.....Metrix has been briefing MPs on 20,000 trainees per year, as the trainee places have shrunk from 6000 to 2700.  Thus courses shortened to 5 or 6 weeks average.  The Western Mail equates 20,000 short-term stayers to a town like Risca, but a large Butlins holiday camp is a better analogy.  Like at Butlins most of the food and other supplies come from far away, and most of the leisure activities are on-site, while employment for locals is in cleaning, security and maintenance.

 Value for Money

Metrix mouthpiece says “inflation has pushed the cost of the project slightly northwards” instead of 30% upwards, to still claim £500M saving over the alternative.  There is no updated financial assessment – the Minister gave £400M more to use the Cosford, Blandford and Gosport sites, with upgraded facilities (2008 Private Eye). Now, with reduced numbers, only two sites would be needed and their cost has inflated perhaps by 10%, so could be £1500-2000M cheaper. The saving through some “1000 military personnel being released back to active duties” comes under any integrated training option (the MoD says 1200 saving).

 

What alternative ?

Metrix mouthpiece says “the upkeep of its aging existing facilities across nine sites”, but the specialist ‘Package 2’ training is remaining within MoD, while the ‘Package 1’ affects 9 sites and allows 2 to be vacated.  Depending on the forces reductions in the Defence Review, Package 1 training would be accommodated on one or both of Cosford or Blandford, plus Gosport Navy training that is to be retained till 2020 or longer in all options.

 

What prospects for WAG’s Aerospace Business Park ?

Metrix mouthpiece says it is hoped “to leverage significant investment from its close proximity to the college – a gross value added of more than £500m annually would be generated”.  This is repetition of the WDA’s failed speculations.  They used to claim “synergy” with DARA, then “complementary” to the Training College , and here only ‘proximity’.  

… aerospace in recession;   no longer in favour with WAG’s low carbon transition.

09/07/2010

MP should argue the case for Cosford more strongly!

MP should argue the case for Cosford more strongly!

Mark Pritchard MP argued for keeping training at Cosford and sending the army logistics brigades to St Athan during Defence Questions in the Commons on 5th July.

Tory MP Mr Pritchard said: “Does it not make sense, given the presence of the extra special forces support group and the 1st Battalion Parachute Regiment and indeed the logistic hangars and the very long runway indeed at RAF St Athan in Wales, to actually have 1 and 2 logistics brigade return to St Athan rather than RAF Cosford in Shropshire?”

The Defence College of Aeronautical Engineering would then stay at Cosford airbase.
While this alternative was not chosen originally, the large down-sizing of the integrated Training College (from 6000 to 2700 or even 2000 trainee places) brings the Cosford option back into reckoning.  Little investment would be needed for the reduced numbers.

Nick Harvey’s ministerial reply showed he’s unaware of the down-sizing and unwilling to make a proper reassessment.  Too much a prisoner of his civil servants!


Cosford training base

A question in parliament on Monday has revealed that there is fresh doubt over the future of RAF Cosford as a military training base. The new coalition government has indicated that it has no intention of halting the plans to construct a defence super-centre in St Athan, Wales.
Mark Pritchard (The Wrekin) (Con): If he will consider, as part of the strategic defence and security review, the merits of the Army returning to RAF St Athan rather than RAF Cosford. [5314]
The Minister for the Armed Forces (Nick Harvey): Plans for the defence training review package 1 project remain unchanged, and consequently it is still planned for 102 Logistics Brigade to relocate to RAF Cosford in 2018 under the BORONA programme. Like everything else in the defence world, that is subject to the strategic defence and security review. At this point, no decisions have been taken.
Mark Pritchard: Let me be clear: Shropshire has a long and proud history of working with the British Army, the Royal Air Force and the Royal Navy, but does it make sense, given the presence of the excellent special forces support group and 1st Battalion the Parachute Regiment, and indeed the logistic hangars and a very long runway indeed at RAF St Athan in Wales, for 102 Logistics Brigade to return to St Athan rather than to RAF Cosford in Shropshire?
Nick Harvey: My hon. Friend is aware that there were two different proposals in the final analysis for the defence training review facilities: Cosford and St Athan. Those were subject to the most detailed scrutiny to decide which was the better fit for our defence requirements and the decision was that the defence training review should relocate facilities to St Athan. We believe that there is an obvious synergy between that and other work at St Athan, particular in high technology, and a lot of work has already gone into preparing for that move. To change course now, as he suggests, would undo a great deal of investment that has already been made and add considerably to the final cost.
The Express and Star report on the recent announcement:
Tuesday 6th July 2010, 11:30AM BST.
Fresh doubt was today cast over the future of RAF Cosford as a military base after the the new coalition Government signalled it had no intention of switching plans to construct a defence super-centre at an air force base in South Wales to the Midlands instead.
Campaigners’ hopes for a reversal of the previous Labour government’s decision have been dashed after Armed Forces Minister Nick Harvey indicated it was out of the question.
The Conservatives promised a review of the transfer if they won power.
Mr Harvey stopped short of guaranteeing the £13bn project currently under way at St Athan would get the green light from the Conservative-Liberal Democrat coalition as part of its strategic defence review, which is expected to be driven by the need to scale back spending.
But said to “change courses” would “add to the final costs considerably”.
In addition, he was unable to shed any further light on shelved plans to move UK troops based in Germany to RAF Cosford – its only other hope of staying alive as a military base.
Plans for the movement of 2,600 troops from Germany to Cosford, due to start in 2016 under Operation Barona, have been delayed to 2018 – putting 400 jobs at the air field near Wolverhampton at risk.
Mr Harvey said the plans were still under review.
His comments came after Telford and Wrekin MP Mark Pritchard urged him to consider the merits of relocating some brigades to St Athan, while suggesting Cosford should remain the principal training centre for the armed forces.
Raising the issue during Defence Questions in the Commons yesterday, Mr Pritchard said: “Shropshire has a long and proud history of working with the British Army, the Royal Air Force and the Royal Navy.
“But does it not make sense, given the presence of the extra special forces support group and the 1st Battalion Parachute Regiment and indeed the logistic hangars and the very long runway indeed at RAF St Athan in Wales, to actually have 1 and 2 logistics brigade return to St Athan rather than RAF Cosford in Shropshire?” asked the Tory MP.
Work is under way to move the Defence College of Aeronautical Engineering (DCAE), currently at Cosford airbase near Shifnal, to Wales from 2014.
Mr Harvey said the decision had been made that St Athan was “better fit for our defence requirements”.
He went on: “We believe there is an obvious synergy between that and other work at St Athan, particularly in high-technology areas.
“To change courses as you suggest now, would undo a great deal of investment that has already been made and add to the final costs considerably,” he added.
Welsh Labour MP Chris Bryant said he was delighted the Government was going to “stick with St Athan”.

17/01/2009

2nd anniverary concerns

On the 2nd “Anniversary” of the decision to let Metrix privatise military training under the auspices of the Defence Training Review (DTR) questions still remain on whether or not the project is affordable. An article in Defence Management Today highlights some of the ongoing concerns:

Two years after the Defence Training Review (DTR) was awarded to the Metrix consortium, the project is slowly making progress towards final approval. Yet major questions remain over the cost, affordability and staffing of this multi-billion pound programme that will revolutionise and transform training in the Armed Forces.

The DTR will centre most non-military technical training in one location- St Athan, Wales, for all three branches of the Armed Forces. When the contract was initially awarded to Metrix in January 2007 there were to be several packages in the programme. However following “affordability gaps” in the contract, the MoD scaled back the programme to one package.

Two years on the DTR is either facing oblivion or is about to dramatically transform the way the Armed Forces trains and operates, depending on who you talk too.

Defence management.com has learned through documents made available under the Freedom of Information Act that the MoD and other public bodies close to the deal knew of the £1bn rise in cost rise nearly a year ago despite the fact that it was not made public for almost six months.

Given the worsening economic conditions, there is no guarantee that costs will be able to be maintained at £12bn accordi ng to The Public and Commercial Services (PCS) union, which has been an outspoken critic of the deal from the outset.

“The budget has risen by at least £1bn in the past 18 months. Given their [the MoD's] record for not keeping things on budget, there is every reason to think that costs will increase further,” said PCS’ Robert O’ Harney, the regional vice chair for the Midlands and spokesperson on the issue of the DTR.

The full article can be viewed here.

25/11/2008

How much will it cost?

NAO Response to DTR Concerns.

News Published by Cheryl under Cosford, MoD

Following a response from Tim Burr NAO Comptroller to Mark Pritchard dated 17th Nov, members are now receiving a cut and paste response from Mark Andrews Director Defence VFM. Of interest in the response, reference to the total cost of the programme being £12billion was announced in Sept to Mark Pritchard, yet John Smith used £12billion in a question in the House in July 21st. Remember it was only in Nov 07 that after question from Liam Fox they admitted it was £11billion. Also if Department told by Metrix in March that there had been significant cost increase and by May it was unaffordable, then why did the Minister on April 21 2008 tell Mark Pritchard that Package 1 would save taxpayers £400million over the life of the contract ? The affordability of DTR remains sceptical given these inconsistencies. Only in this Country can the NAO decide to investigate after the horse has bolted i.e contract signature.




10/10/2008

DTR Non announcement

DTR - Non Announcement

Published by Cheryl under Cosford, MoD

Yesterday the Shropshire Star had the following to say about the defence debate in the house of commons:

Thursday the 9th of October was another “non announcement” on the future of Package 1 DTR from the Minister for the Armed Forces Bob Ainsworth. Local MP’s Mark Pritchard both asked questions during the debate, an ad hoc version is below. Of interest was the fact that none of the Welsh MP’s made any comment.”PCS Branch Official H O’Harney at Cosford said “The news that further delays in the programme did not come as a shock to the staff at Cosford, they have been waiting for years to have clarification on their futures .The MoD seem hell bent on moving to Wales at all cost and the sooner the National Audit Office or Publics Account Committee review this programme the better since PCS are still skeptical that DTR is affordable. A £12 billion PFI carrying on in this current finacial crisis seems ridiculous given the risks and affordability issues. Our members at Cosford have made it clear that they have no intention to move Wales and the risk to the training of the Armed Forces is still real. It would appear that the MoD want to privatise at all cost despite the huge risks”

The response to a question, by the astute MP Mark Pritchard, Mr. Ainsworth: I am sure that the hon. Gentleman has a national interest too, but he has a particular interest in this matter and, obviously, he pursues it. I am not saying that the costs have not changed. I am saying that we still have an affordable package that is far cheaper than the alternatives, and that has been worked on over the summer. We will be able to go ahead with defence package 1 and get value for money out of those proposals…..

This is another first for the DTR programme in suggesting that the “fallback posistion” is more expensive than the proposed move to St Athan !! No wonder the Department needs to give Metrix another six months grace to rearrange costings to fit. It is also of note that in the preamble issued to staff that the MoD have stated that the sale of additional sites plays no part in enabling the move to ahead. Strangely in their own Risk Assessment which was featured in the Private Eye magazine, this was one the MoD’s identified risks. The fact that the DTR IPT can try to spin another 6 month delay is a positive message to all the staff is ludicrous !! PCS will continue to campaign against this looming financial disaster.

16/09/2008

St Athan Deal collapsing?

RAF base may stay open due to DTR
Monday, September 15, 2008
The future of RAF Cosford is even more unclear than it was a few months ago due to the struggles of the Defence Training Review (DTR).

The £11bn training programme was awarded to St Athan, Wales over the RAF base in Shropshire. Many officials expected that this would mean the closure of the airbase. A formal announcement on the base's future is expected later this month.

However, as reported on Friday, the DTR is facing an extended period of difficulty and a full blown financial review because its financing was dependent on the sale of surplus MoD land.

Now the MoD may have to keep the RAF Cosford open as a contingency plan in case the deal at St Athan collapses. RAF Cosford had a number of advocates behind it during the bidding of the DTR including the unions representing the trainers and a number of high profile MPs. The base's infrastructure and close proximity to major cities and airports continues to make an attractive option. If the deal at St Athan were to fall through, the MoD would need a backup site for the programme.

Funding the continued operation of RAF Cosford may pose additional challenges to the MoD. A few months ago all signs pointed to it being closed and sold off. Keeping the base open will not only cost additional money but force the ministry to keep certain jobs there.




27/08/2008

St Athan latest news - next meeting

1.Next meeting Mon 8th Sept 6pm Temple of Peace

2.Cosford letter to audit office

3. MP Calls for St Athan Rail Stop (oh yeah!)

4. Defence Training Review Over Budget

5. See the Private Eye article ...

The full article can be viewed here.

1. Look forward to seeing you at the next meeting at Temple of Peace 6pm Mon 8th Sept...please send items for the agenda.


2. Cosford letter to audit office

please download or use this copy below and send in and a copy to your AM and MP would be useful

Telephone Please reply to:

INSERT YOUR NAME AND ADDRESS

To: Tim Burr
Comptroller and Auditor General
Private Office
National Audit Office
157-197 Buckingham Palace Road
London
SW1W 9SP
_______________________________

DEFENCE TRAINING REVIEW COSTS TO DATE

Dear Mr Burr,

I am writing to you concerning Package One of the Defence Training Review (DTR) Transformation programme, which is a programme worth some £12 Billion allegedly. It will be one of the most expensive PFI/PPP’s project ever undertaken by the Ministry of Defence and will be amongst the largest partnering arrangement ever undertaken in the United Kingdom and yet to date the NAO has never reported on this matter. I am extremely concerned about the escalating cost to the taxpayer that this project is incurring. I am aware to the vast amount of money being spent on consultants, some of whom are being paid at £1200 a day. The contract’s length of 30 years and the unheard of first breakpoint at fifteen years is a recipe for spiralling costs and a major impact upon the public purse.


I believed the MoD option selected for delivery of defence training would depend upon what is best for defence, combining both operational and value for money considerations. Work on this programme has been going on since 2001. To date every deadline has passed with announcements of further delays, which must increasingly mean additional expenditure of public monies. In July 2008 in the House of Commons, Minister Bob Ainsworth said “the financial appraisals have thrown up some difficult issues” ! He also talked about “affordability issues”, presumably the same “affordability issues” as mentioned by his predecessors Tom Watson, Don Touhig and Ivor Caplin who also knew that this programme is unaffordable.

You should also be aware that public monies were spent on Package 2 of DTR in trying to get a PPP/PFI solution, only for this to fall apart on “affordability issues” How much public money was spent on this failure and considering that the MOD have just given another few hundreds of millions pound to Package 2 to develop a different approach, it is disturbing to know that you have never audited the accounts of the MoD on this matter. Indeed your own literature states”The role of the National Audit Office is to audit the accounts of all government departments and agencies as well as a wide range of other public bodies, and report to Parliament on the economy, efficiency and effectiveness with which these bodies have used public money.”

Therefore I would request that as a matter of urgency the NAO conduct an enquiry or investigation into this programme as you had originally timetabled for in 2008/2009.

I look forward to your reply.

Yours sincerely,
.............................................................

3. MP Calls for St Athan Rail Stop

Published by Cheryl under Cosford, MoD

Yesterdays article reported that the cost of the Defence Trainining Review had now increased by £1bn to £13bn. An article on WalesOnLine reports that Vale of Glamorgan MP John Smith is calling for a dedicated rail stop to be built at St Athan, which will add more cost to the project. He thinks this will benefit the Welsh economy and ease congestion:

A DEDICATED rail stop should be built to serve the Defence Technical Academy in St Athan, Vale of Glamorgan MP John Smith has said.

Thousand of trainees from the Army, Royal Navy and Royal Air Force will attend the £13bn academy.

Mr Smith said: “In order for the Welsh economy to take full advantage from this record investment, the St Athan site must be served by an improved transport system.

“There are operational railway tracks running within very close proximity to the site. I believe there is a very strong case for building a dedicated rail stop at the academy. It will help reduce road traffic congestion, and prevent commuters and visitors to the academy the inconvenience of having to get off at Rhoose or Llantwit Major stations and transfer to a bus shuttle service.

“I will be writing to the Welsh Assembly Government, the local planning authority and the consortium responsible for building the academy asking them to consider building a rail halt at the site for the good of the Welsh economy.”

In addition WalesOnLine reports that a proposed road link that will service St Athan could cost up to £135m of tax payers money. Currently there are approximately 600 Civil Servants plus many military and private sector workers employed at RAF Cosford, the majority of these staff would be expected to move from Cosford to St Athan if the Metrix plans go ahead. Cosford is situated 800 meters from a motorway and already has it’s own railway station.

Is it right that so much taxpayers money is needed to support the Metrix bid is surely a question that needs to be asked. This is another reason that we are asking members to write to the NAO and get them to scrutinise this project which has already cost the tax payer millions in wasted consultant fees.

No responses yet

Aug 22 2008

4. Defence Training Review Over Budget

Published by Cheryl under Cosford, MoD

The latest edition of Private Eye reports that Brigadier Geoff Nield has let it slip that the cost of the Defence Training Review programme had gone up and is now over budget.

At a local “Stakeholders” meeting in the Vale of Glamorgan, home to a proposed new defence academy, the Ministry of Defence’s officer in charge, Brigadier Geoff Nield, let slip that the price had gone up from £11bn to £ 12bn. As the deal was slated to save the MoD just £400m at the old price, it seems the scheme will not only expose the armed forces to serious operational risks (see Eye 1213) but will actually cost the taxpayer hundreds of millions more than keeping training in-house.

The increasing delays to implementing the project has led to the National Audit Office (NAO) pulling its plans to investigate the deal. Members are encouraged to write to the NAO requesting that they undertake a review of the public monies spent on DTR. There is a link to a sample letter below, this can be amended as you feel fit.